What are the critical path activities?

A project to remodel an office area has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
Activity
Duration
Predecessors
A
3 months
---
B
2 months
---
C
3 months
---
D
4 months
A, B
E
3 months
A
F
2 months
B, C
G
2 months
F
H
1 month
G
I
4 months
D, E, F
J
5 months
H
a) What are the critical path activities? (5 points) b) What is the project's scheduled completion time? (5 points) c) What is the slack or float for Activity B? Show your calculations. (5 points) d) What is the slack or float for Activity C? Show your calculations. (5 points) e) What is the slack or float for Activity E? Show your calculations. (5 points) f) What is the slack or float for Activity H? Show your calculations.

6 HOUR ESSAYS ALSO AVAILABLE!!!! CLICK HERE TO REQUEST THIS PAPER

Popular posts from this blog

Competency vs. Insanity

Fort Mitchell, Alabama Adult Day Care Center

Common Elements of Religion